Before the preliminary design: design brief and surveys
The input for the preliminary design includes the client’s design brief, a building survey and, where needed, a sketch design or a process design [Mr 97 § 8(2)]. In the design brief the client describes what they need: rooms, areas, budget and deadline. A sketch design is a simple massing and layout solution. It is used to test whether the idea works before the bigger work begins [EVS 932:2017, Annex A].
If a detailed spatial plan has been adopted for the property, the design must comply with it [EhS § 42(1)]. If there is no obligation to prepare a detailed spatial plan, design criteria are needed to erect a building that requires a building permit or to expand it by more than 33% [EhS § 26(1) and (2)]. They are issued by the local authority [EhS § 28(1)]. More in the guide building permit or building notice.
Preliminary design: what and where
The preliminary design presents the architectural solution of the building and the principles of the engineering solutions [Mr 97 § 8(1)]. At this stage options are compared and the most suitable one is chosen [Mr 97 § 8(3)]. The preliminary design must make it possible to determine the energy performance of the building and its approximate construction cost [Mr 97 § 8(5)].
The site plan, architecture and fire safety are presented both in the explanatory memorandum and in drawings. Interior architecture, landscape architecture and engineering solutions are described at least in the explanatory memorandum [Mr 97 § 8(9)].
When applying for a building permit, the applicant chooses at which stage to submit the design. The competent authority assesses it against the requirements for a preliminary design [Mr 97 § 13(1)] [Mr 97 § 13(2)]. A preliminary design is therefore enough to apply for a building permit [EVS 932:2017, p. 19, diagram 2].
Main design: from what and how precisely
The solutions of the main design are precise enough to prepare a budget, organise a construction tender and ask for price quotes [Mr 97 § 9(1)]. The solutions must be checked and consistent with each other [Mr 97 § 9(4)].
Materials and equipment are given technical requirements, but the manufacturer is generally not named [Mr 97 § 9(5)]. This lets contractors offer an equivalent product and makes the bids comparable.
Detailed design: how to build
The detailed design is precise enough to build correctly from it [Mr 97 § 10(1)]. It states the grades and manufacturers of materials [Mr 97 § 10(8)]. The drawings are at a scale and in a format that is convenient to use on site [Mr 97 § 10(5)].
Construction work is based on the detailed design [EVS 932:2017, p. 17].
The three stages side by side
| Stage | Preliminary design | Main design | Detailed design |
|---|---|---|---|
| Answers the question | What and where? | From what and how precisely? | How to build? |
| Use | Building permit application | Budget, construction tender, price quote | Construction |
| Cost | Approximate | Budget-level | – |
| Products | Principles of the solution | Technical requirements, manufacturer generally not named | Grade and manufacturer |
| Source | [Mr 97 § 8] [Mr 97 § 13] | [Mr 97 § 9] | [Mr 97 § 10] |
What does the client do at each stage?
The designer submits the solutions of each stage to the client for approval [Mr 97 § 5(2)]. An approved stage is the binding brief for the next stage [Mr 97 § 5(3)]. That is why changing the solution is cheapest in the preliminary design. During the detailed design every change means redoing several parts of the design.
Are all three always needed?
The building permit applicant submits the design at the stage of their choice [Mr 97 § 13(1)]. The application must be accompanied by building design documentation that meets the requirements [EhS § 40(3)]. The number and content of the stages are agreed in the design contract. For a listed heritage building, the National Heritage Board may require a specific stage in its special conditions [MuKS § 50(4) 5)].
Changes in the law
We check the provisions cited in this guide every week in the State Gazette (Riigi Teataja) and in draft acts before the Riigikogu. Last checked 11 October 2026.
No known changes currently affect this guide.
Sources
- Building Code (EhS), consolidated text in force from 01.10.2026 (in Estonian)
- EhS Annex 1 “Table on the obligation of a building notice, building design documentation and a building permit”, amended RT I, 11.07.2026, 3, in force from 01.08.2026 (PDF, in Estonian)
- EhS Annex 2 “Table on the obligation of a use and occupancy notice, building design documentation and a use and occupancy permit”, amended RT I, 11.07.2026, 3, in force from 01.08.2026 (PDF, in Estonian)
- Regulation No. 97 of the Minister of Economic Affairs and Infrastructure of 17.07.2015 “Requirements for building design documentation” (Mr 97), consolidated text in force from 01.01.2025 (in Estonian)
- Heritage Conservation Act (MuKS), consolidated text in force from 01.10.2025 (in Estonian)
- EVS 932:2017 “Ehitusprojekt” (building design documentation)
Validity of the legislation checked in the Riigi Teataja (State Gazette) on 08.10.2026. This guide does not replace the position of the competent authority. The requirements for a specific building are set by the local authority.