How long does it take to get a building permit?

The local authority issues a building permit within 30 days of the application. The road from idea to use, however, includes several procedures. Here are the statutory time limits in one place.

Legislation checked 08.10.2026 · Reading time 3 min · Nool Projekt OÜ

Abbreviations: EhS – Building Code (ehitusseadustik); MuKS – Heritage Conservation Act (muinsuskaitseseadus); § – section, (2) – subsection, 1) – clause.

Procedure time limits

ProcedureTime limitValiditySource
Design criteria30 days from the application, 60 days in an open procedure5 years [EhS § 31(2)] [EhS § 33(1)]
Heritage conservation special conditions30 days from receipt of a compliant application, 60 days from the application in an open procedure5 years, extendable once by 5 years in justified cases [MuKS § 51(3)] [MuKS § 51(5)]
Building noticeSubmit at least 10 days before construction startsConstruction may be carried out within 4 years [EhS § 36(2)] [EhS § 37]
Building permit30 days from the application5 years, 7 years once construction has started [EhS § 42(5)] [EhS § 45(1)]
National Heritage Board work permit30 days from receipt of a compliant applicationUp to 5 years, extendable once by up to 5 years in justified cases [MuKS § 54(2)] [MuKS § 54(6)]
Notice of commencement of construction (building that requires a building permit)Submit at least 3 days before construction starts– [EhS § 43(1)]
Use and occupancy noticeSubmit at least 10 days before useNo expiry [EhS § 48(2)] [EhS § 49]
Use and occupancy permit30 days from the applicationNo expiry unless the permit states otherwise [EhS § 54(4)] [EhS § 56]

What makes the procedure longer?

The 30 days for a building permit are counted from the day the application is submitted [EhS § 42(5)]. The competent authority checks that the application meets the requirements when it receives it [EhS § 41]. Fixing deficiencies takes extra time. If issuing the permit is clearly impossible, the application is left unprocessed [EhS § 41].

Approving and consulted authorities have up to 10 days [EhS § 42(5)]. If an approving authority neither replies nor asks for an extension within 10 days, the application is deemed approved [EhS § 42(9)].

The procedure for heritage conservation special conditions is suspended if the Board first requires a study. The procedure resumes once a compliant study report has been submitted [MuKS § 50(5)].

Example: a detached house without a detailed spatial plan

The detached house has a ground projection area of 140 m². There is no obligation to prepare a detailed spatial plan. The building needs a building permit [EhS Annex 1 (PDF)] and design criteria [EhS § 26(1) and (2)].

  1. Design criteria: up to 30 days [EhS § 31(2)].
  2. Sketch design and preliminary design. The time depends on the scope and on how quickly the client approves the solutions.
  3. Building permit: up to 30 days [EhS § 42(5)]. The detailed design can be prepared at the same time, but any changes made during the procedure must be carried over into it.
  4. Notice of commencement of construction: at least 3 days before work starts [EhS § 43(1)].
  5. Construction.
  6. Use and occupancy notice: at least 10 days before you start using the building [EhS § 48(2)]. A detached house does not need a use and occupancy permit [EhS Annex 2 (PDF)].

In this example the statutory time limits add up to about 73 days: 30 + 30 + 3 + 10. An open procedure or additional checks take longer. The rest is design and construction time.

How long does the design take?

The design time depends on the size of the building, the stages and how quickly the solutions are approved. The content of the stages is explained in the guide preliminary, main and detailed design. We agree on the scope, extent, price and deadlines before the work starts and put them in writing.

Changes in the law

We check the provisions cited in this guide every week in the State Gazette (Riigi Teataja) and in draft acts before the Riigikogu. Last checked 11 October 2026.

Upcoming

Faster planning and building procedures (draft act 949 SE)Draft act

Draft act before the Riigikogu: first reading completed on 30 September 2026, deadline for amendments 14 October 2026. Planned entry into force 1 January 2027.

ProvisionNowUnder the draft
Building Code § 10¹ (new)No such provision.Principle of procedural economy: facts relevant to the application are established as early as possible, and comments on deficiencies are given together in one batch.

Effect on this guide: Under the current text of the draft, the Building Code time limits in this guide (30 days for a building permit and for design criteria, 10 days for approving parties) do not change. The new principle should reduce repeated rounds of comments that currently prolong the procedure. The Planning Act amendments set clearer time limits for initiating and processing a detailed plan. The draft may still change in the Riigikogu.

Draft act 949 SE on the Riigikogu website (in Estonian)

Sources

  1. Building Code (EhS), consolidated text in force from 01.10.2026 (in Estonian)
  2. EhS Annex 1 “Table on the obligation of a building notice, building design documentation and a building permit”, amended RT I, 11.07.2026, 3, in force from 01.08.2026 (PDF, in Estonian)
  3. EhS Annex 2 “Table on the obligation of a use and occupancy notice, building design documentation and a use and occupancy permit”, amended RT I, 11.07.2026, 3, in force from 01.08.2026 (PDF, in Estonian)
  4. Regulation No. 97 of the Minister of Economic Affairs and Infrastructure of 17.07.2015 “Requirements for building design documentation” (Mr 97), consolidated text in force from 01.01.2025 (in Estonian)
  5. Heritage Conservation Act (MuKS), consolidated text in force from 01.10.2025 (in Estonian)
  6. EVS 932:2017 “Ehitusprojekt” (building design documentation)

Validity of the legislation checked in the Riigi Teataja (State Gazette) on 08.10.2026. This guide does not replace the position of the competent authority. The requirements for a specific building are set by the local authority.

Guides

Read also

All guides
Guide · 4 min Building permit or building notice: what does your building need? Ground projection area, height and the type of work decide. Tables valid from 01.08.2026. Read the guide Guide · 3 min Preliminary, main and detailed design: what is the difference? Three stages, three purposes: building permit, price quotes and construction. Read the guide