Procedure time limits
| Procedure | Time limit | Validity | Source |
|---|---|---|---|
| Design criteria | 30 days from the application, 60 days in an open procedure | 5 years | [EhS § 31(2)] [EhS § 33(1)] |
| Heritage conservation special conditions | 30 days from receipt of a compliant application, 60 days from the application in an open procedure | 5 years, extendable once by 5 years in justified cases | [MuKS § 51(3)] [MuKS § 51(5)] |
| Building notice | Submit at least 10 days before construction starts | Construction may be carried out within 4 years | [EhS § 36(2)] [EhS § 37] |
| Building permit | 30 days from the application | 5 years, 7 years once construction has started | [EhS § 42(5)] [EhS § 45(1)] |
| National Heritage Board work permit | 30 days from receipt of a compliant application | Up to 5 years, extendable once by up to 5 years in justified cases | [MuKS § 54(2)] [MuKS § 54(6)] |
| Notice of commencement of construction (building that requires a building permit) | Submit at least 3 days before construction starts | – | [EhS § 43(1)] |
| Use and occupancy notice | Submit at least 10 days before use | No expiry | [EhS § 48(2)] [EhS § 49] |
| Use and occupancy permit | 30 days from the application | No expiry unless the permit states otherwise | [EhS § 54(4)] [EhS § 56] |
What makes the procedure longer?
The 30 days for a building permit are counted from the day the application is submitted [EhS § 42(5)]. The competent authority checks that the application meets the requirements when it receives it [EhS § 41]. Fixing deficiencies takes extra time. If issuing the permit is clearly impossible, the application is left unprocessed [EhS § 41].
Approving and consulted authorities have up to 10 days [EhS § 42(5)]. If an approving authority neither replies nor asks for an extension within 10 days, the application is deemed approved [EhS § 42(9)].
The procedure for heritage conservation special conditions is suspended if the Board first requires a study. The procedure resumes once a compliant study report has been submitted [MuKS § 50(5)].
Example: a detached house without a detailed spatial plan
The detached house has a ground projection area of 140 m². There is no obligation to prepare a detailed spatial plan. The building needs a building permit [EhS Annex 1 (PDF)] and design criteria [EhS § 26(1) and (2)].
- Design criteria: up to 30 days [EhS § 31(2)].
- Sketch design and preliminary design. The time depends on the scope and on how quickly the client approves the solutions.
- Building permit: up to 30 days [EhS § 42(5)]. The detailed design can be prepared at the same time, but any changes made during the procedure must be carried over into it.
- Notice of commencement of construction: at least 3 days before work starts [EhS § 43(1)].
- Construction.
- Use and occupancy notice: at least 10 days before you start using the building [EhS § 48(2)]. A detached house does not need a use and occupancy permit [EhS Annex 2 (PDF)].
In this example the statutory time limits add up to about 73 days: 30 + 30 + 3 + 10. An open procedure or additional checks take longer. The rest is design and construction time.
How long does the design take?
The design time depends on the size of the building, the stages and how quickly the solutions are approved. The content of the stages is explained in the guide preliminary, main and detailed design. We agree on the scope, extent, price and deadlines before the work starts and put them in writing.
Changes in the law
We check the provisions cited in this guide every week in the State Gazette (Riigi Teataja) and in draft acts before the Riigikogu. Last checked 11 October 2026.
Upcoming
Draft act before the Riigikogu: first reading completed on 30 September 2026, deadline for amendments 14 October 2026. Planned entry into force 1 January 2027.
| Provision | Now | Under the draft |
|---|---|---|
| Building Code § 10¹ (new) | No such provision. | Principle of procedural economy: facts relevant to the application are established as early as possible, and comments on deficiencies are given together in one batch. |
Effect on this guide: Under the current text of the draft, the Building Code time limits in this guide (30 days for a building permit and for design criteria, 10 days for approving parties) do not change. The new principle should reduce repeated rounds of comments that currently prolong the procedure. The Planning Act amendments set clearer time limits for initiating and processing a detailed plan. The draft may still change in the Riigikogu.
Sources
- Building Code (EhS), consolidated text in force from 01.10.2026 (in Estonian)
- EhS Annex 1 “Table on the obligation of a building notice, building design documentation and a building permit”, amended RT I, 11.07.2026, 3, in force from 01.08.2026 (PDF, in Estonian)
- EhS Annex 2 “Table on the obligation of a use and occupancy notice, building design documentation and a use and occupancy permit”, amended RT I, 11.07.2026, 3, in force from 01.08.2026 (PDF, in Estonian)
- Regulation No. 97 of the Minister of Economic Affairs and Infrastructure of 17.07.2015 “Requirements for building design documentation” (Mr 97), consolidated text in force from 01.01.2025 (in Estonian)
- Heritage Conservation Act (MuKS), consolidated text in force from 01.10.2025 (in Estonian)
- EVS 932:2017 “Ehitusprojekt” (building design documentation)
Validity of the legislation checked in the Riigi Teataja (State Gazette) on 08.10.2026. This guide does not replace the position of the competent authority. The requirements for a specific building are set by the local authority.