Three questions before the table
- What work is being done? The columns of Annex 1 are erection, remodelling of a building service system, remodelling or expansion by up to 33%, expansion by more than 33%, replacement of an individual part with an equivalent one, and demolition.
- How big and how tall is the building? What counts is the ground projection area and the height. 20.0 m² still falls in the lower class, 20.1 m² is already in the next one [EhS Annex 1 (PDF)].
- What kind of building is it? A detached house and a two-apartment residential building (use codes 11100 and 11210) and their ancillary buildings have lighter requirements than other buildings [EhS Annex 1 (PDF)].
The class is chosen by the end result of the work. If an 18 m² building is expanded to 25 m², the “20–60 m²” row applies [EhS Annex 1 (PDF)]. This rule does not apply to demolition [EhS Annex 1 (PDF)].
Detached house, two-apartment residential building and ancillary building
| Ground projection area and height | Erection | Expansion by more than 33% | Remodelling or expansion by up to 33% | Demolition |
|---|---|---|---|---|
| up to 20 m², up to 5 m | Not required | Not required | Not required | Not required |
| 20–60 m², up to 5 m | Notice + design | Notice + design | Building notice | Notice + design |
| up to 60 m², over 5 m | Building permit | Building permit | Notice + design | Notice + design |
| over 60 m² | Building permit | Building permit | Notice + design | Notice + design |
Source: [EhS Annex 1 (PDF)]. Use codes 11100 and 11210.
Other residential and non-residential buildings
| Ground projection area and height | Erection | Expansion by more than 33% | Remodelling or expansion by up to 33% | Demolition |
|---|---|---|---|---|
| up to 20 m², up to 5 m | Not required | Not required | Not required | Not required |
| 20–60 m², up to 5 m | Notice + design | Notice + design | Notice + design | Notice + design |
| up to 60 m², over 5 m | Building permit | Building permit | Notice + design | Building permit |
| over 60 m² | Building permit | Building permit | Building permit | Building permit |
Source: [EhS Annex 1 (PDF)]. For example apartment buildings, office, commercial, industrial and warehouse buildings.
“Notice + design” means that the building notice must be accompanied by building design documentation [EhS § 36(4)]. Replacing an individual part of a building with an equivalent one needs neither a notice nor a permit. To remodel a building service system in a private house of 20–60 m² and up to 5 m tall, a building notice is enough. For a building up to 20 m² and up to 5 m tall, neither is needed. In other cases you need a building notice with building design documentation [EhS Annex 1 (PDF)].
Design criteria and detailed spatial plan
If no detailed spatial plan has to be prepared for a building that requires a building permit, design criteria are needed before the building design documentation can be prepared [EhS § 26(1)]. They are issued for erecting a building and for expanding it by more than 33% of its originally planned volume [EhS § 26(2)]. Design criteria are issued by the local authority [EhS § 28(1)] and are valid for five years [EhS § 33(1)].
If a detailed spatial plan has been adopted for the property, the building design must comply with it [EhS § 42(1)].
Listed heritage building
To prepare building design documentation for a cultural monument or a building in a heritage conservation area, you need special conditions from the National Heritage Board [MuKS § 50(1)]. Conservation, restoration, construction and changes to the appearance require a work permit from the Board [MuKS § 52(1)]. The local authority coordinates the building notice and the building permit with the Board [MuKS § 52(4)].
Maintenance and repairs do not need a work permit [MuKS § 52(7) 1)].
The local authority may require more
In justified cases the competent authority may require a building notice or a building permit even for a structure that is not listed in Annex 1 [EhS § 35(4)] [EhS § 38(3)]. The authority then weighs how hazardous the structure is and its impact on public space and on other people’s rights, and compares these with similar parameters in Annex 1.
If a project that requires a building permit also includes structures that require a building notice, the building permit application replaces the building notice [EhS § 35(5)].
After construction: use and occupancy notice or permit
Annex 2 determines whether a use and occupancy notice is enough to start using a completed building or whether a use and occupancy permit is needed. For a detached house and a two-apartment residential building a use and occupancy notice is enough; they do not need a use and occupancy permit [EhS Annex 2 (PDF)]. For other residential and non-residential buildings, erecting a building over 5 m tall or over 60 m² requires a use and occupancy permit [EhS Annex 2 (PDF)].
Time limits are in the guide how long does it take to get a building permit.
Changes in the law
We check the provisions cited in this guide every week in the State Gazette (Riigi Teataja) and in draft acts before the Riigikogu. Last checked 11 October 2026.
No known changes currently affect this guide.
Sources
- Building Code (EhS), consolidated text in force from 01.10.2026 (in Estonian)
- EhS Annex 1 “Table on the obligation of a building notice, building design documentation and a building permit”, amended RT I, 11.07.2026, 3, in force from 01.08.2026 (PDF, in Estonian)
- EhS Annex 2 “Table on the obligation of a use and occupancy notice, building design documentation and a use and occupancy permit”, amended RT I, 11.07.2026, 3, in force from 01.08.2026 (PDF, in Estonian)
- Regulation No. 97 of the Minister of Economic Affairs and Infrastructure of 17.07.2015 “Requirements for building design documentation” (Mr 97), consolidated text in force from 01.01.2025 (in Estonian)
- Heritage Conservation Act (MuKS), consolidated text in force from 01.10.2025 (in Estonian)
- EVS 932:2017 “Ehitusprojekt” (building design documentation)
Validity of the legislation checked in the Riigi Teataja (State Gazette) on 08.10.2026. This guide does not replace the position of the competent authority. The requirements for a specific building are set by the local authority.